ADR Partnership

Utilities and building services

HK Airport, Midfield APM System

HK Airport, Midfield APM System

The complete design, supply, manufacture, installation, testing and commissioning for extension of the T1 Line to the new Midfield Concourse (MFC) together with a Route Recovery System between the MFC APM Station and T1 West Hall APM Station. These works included upgrading the existing APM T1 Line signalling system with Communication Based Train Control (CBTC) technology. ADR provided commercial support in the valuation and negotiation of variations to the works with the Employer and Specialist Subcontractors.

MEP works to the Central-Wan Chai Bypass Tunnel

MEP works to the Central-Wan Chai Bypass Tunnel

Construction of tunnel buildings, installation of route-wide electrical and mechanical works and TCSS, and associated works for tunnel commissioning. MEP works included ventilation and air purification systems, tunnel and approach road lighting, central control monitoring and surveillance systems, plumbing, drainage and fire services. ADR provided a commercial review of potential claims and variation recovery strategy.

Tamar Development Project

Tamar Development Project

Tamar Development project comprised the design and construction of the Central Government Complex Office Block, the Legislative Council Complex and an open space of not less than two hectares, two covered foot bridges and other ancillary facilities. ADR carried out a commercial review for the Building Services (E&M) sub-contractor and prepared claims for delay and disruption, advising on various commercial and contractual issues.

Tsuen Wan Drainage Tunnel

Tsuen Wan Drainage Tunnel

Tsuen Wan Drainage Tunnel project is part of drainage improvement works in the Tsuen Wan and Kwai Chung districts of Hong Kong SAR by Drainage Services Department. The Works involved the design and construction of a tunnel of about 5.1 kilometres in length with an internal diameter of 6.5 metres using a TBM, and construction of three intake structures and an outfall structure with associated landscaping and civil works. ADR carried out a commercial review of the contract documents, prepared claims for delay and disruption for the main contractor and also advised on various contractual matters.

Lai Chi Kok Transfer Scheme

Lai Chi Kok Transfer Scheme

The Lai Chi Kok transfer scheme comprises the construction of a 3.7 kilometre long tunnel, 4.9 metres in diameter from Chak On Estate to Victoria Harbour near Stonecutters Island. The Works also consisted of a stilling basin and outfall structure, six intakes and about 270 metres of connection adit tunnels, slope stabilization works and ancillary works. ADR carried out a commercial review of Geotechnical Baseline Report (GBR), prepared claims for delay and disruption for the main contractor including issues relating to unforeseen ground conditions and TBM tunneling.

Sludge Treatment Facilities

Sludge Treatment Facilities

Sludge Treatment Facility is a specialist process plant facility carried out as a design, build, operation, maintenance and renewal project. The facility included the construction of two plants, each with two incinerators and a capacity of 1,000 tonnes per day. Each of the plants includes two incineration trains and a steam turbine. ADR prepared claims for extensions of time and for additional payment for the main contractor, including for restrictions on the importation of labour.

Tolo Harbour Sewerage of Unsewered Area Stage I Phase IIB

Tolo Harbour Sewerage of Unsewered Area Stage I Phase IIB

Tolo Harbour Sewerage project comprised the construction of gravity / pressure sewerage systems, pumping stations, sewer crossings and footpaths, cycle tracks, retaining walls and minor roadworks. ADR undertook an independent review of the Contractor’s claims.

Sino Iron Power Plant, Australia

Sino Iron Power Plant, Australia

Sino Iron Power Plant comprised the construction of 2 x 50MW power plants in Perth, Western Australia. ADR prepared an independent report for the main contractor for use in a successful adjudication with respect to increased quantities of rock excavation. ADR also advised the main contractor on claims for additional payment for management of change, prolongation and disruption.

Shatin Sewage Treatment Works

Shatin Sewage Treatment Works

The project comprised the upgrading and modification of Shatin sewage treatment works. ADR prepared claims for the main contractor with respect to delays and disruption to the construction works caused by variations and the late receipt of information, together with claims for additional payment.

Projects

Infrastructure Hong Kong

Infrastructure works

tunnels, rail, airports, roads and bridges. more

Utilities and building services< Hong Kong

Utilities and building services

power stations, sewerage treatment works, water treatment plants and E&M installations. more

Piling and earthworks Hong Kong

Piling and earthworks

foundations, reclamations and site formation. more

Building Hong Kong

Building works

commercial and residential developments. more

<
Tseung Kwan O to Lam Tin Tunnel

Tseung Kwan O to Lam Tin Tunnel

Tseung Kwan O to Lam Tin Tunnel is a dual two-lane highway... more

HK Airport 3 Runway System Project – Reclamation Works

HK Airport 3 Runway System Project – Reclamation Works

Formation of 650 hectares of land north of the existing airport... more

Hong Kong Boundary Crossing Facilities – Passenger Control Building

Hong Kong Boundary Crossing Facilities

The Contractor entered into two Contracts with the... more

East Kowloon Cultural Centre

East Kowloon Cultural Centre

The construction of a nine storey cultural centre block... more

Liantang Boundary Control Point

Liantang Boundary Control Point

The Liantang Boundary Control Point includes the... more

Britcham Ball 2019, The Grand Hyatt

Staff and guests enjoy the ‘Now that’s what I call music’ themed event... more

Bored Piling Hong Kong

Bored Piling

Case Study: Bored Piling. more