Infrastructure works
tunnels, rail, airports, roads and bridges. more
The complete design, supply, manufacture, installation, testing and commissioning for extension of the T1 Line to the new Midfield Concourse (MFC) together with a Route Recovery System between the MFC APM Station and T1 West Hall APM Station. These works included upgrading the existing APM T1 Line signalling system with Communication Based Train Control (CBTC) technology. ADR provided commercial support in the valuation and negotiation of variations to the works with the Employer and Specialist Subcontractors.
Construction of tunnel buildings, installation of route-wide electrical and mechanical works and TCSS, and associated works for tunnel commissioning. MEP works included ventilation and air purification systems, tunnel and approach road lighting, central control monitoring and surveillance systems, plumbing, drainage and fire services. ADR provided a commercial review of potential claims and variation recovery strategy.
Tamar Development project comprised the design and construction of the Central Government Complex Office Block, the Legislative Council Complex and an open space of not less than two hectares, two covered foot bridges and other ancillary facilities. ADR carried out a commercial review for the Building Services (E&M) sub-contractor and prepared claims for delay and disruption, advising on various commercial and contractual issues.
Tsuen Wan Drainage Tunnel project is part of drainage improvement works in the Tsuen Wan and Kwai Chung districts of Hong Kong SAR by Drainage Services Department. The Works involved the design and construction of a tunnel of about 5.1 kilometres in length with an internal diameter of 6.5 metres using a TBM, and construction of three intake structures and an outfall structure with associated landscaping and civil works. ADR carried out a commercial review of the contract documents, prepared claims for delay and disruption for the main contractor and also advised on various contractual matters.
The Lai Chi Kok transfer scheme comprises the construction of a 3.7 kilometre long tunnel, 4.9 metres in diameter from Chak On Estate to Victoria Harbour near Stonecutters Island. The Works also consisted of a stilling basin and outfall structure, six intakes and about 270 metres of connection adit tunnels, slope stabilization works and ancillary works. ADR carried out a commercial review of Geotechnical Baseline Report (GBR), prepared claims for delay and disruption for the main contractor including issues relating to unforeseen ground conditions and TBM tunneling.
Sludge Treatment Facility is a specialist process plant facility carried out as a design, build, operation, maintenance and renewal project. The facility included the construction of two plants, each with two incinerators and a capacity of 1,000 tonnes per day. Each of the plants includes two incineration trains and a steam turbine. ADR prepared claims for extensions of time and for additional payment for the main contractor, including for restrictions on the importation of labour.
Tolo Harbour Sewerage project comprised the construction of gravity / pressure sewerage systems, pumping stations, sewer crossings and footpaths, cycle tracks, retaining walls and minor roadworks. ADR undertook an independent review of the Contractor’s claims.
Sino Iron Power Plant comprised the construction of 2 x 50MW power plants in Perth, Western Australia. ADR prepared an independent report for the main contractor for use in a successful adjudication with respect to increased quantities of rock excavation. ADR also advised the main contractor on claims for additional payment for management of change, prolongation and disruption.
The project comprised the upgrading and modification of Shatin sewage treatment works. ADR prepared claims for the main contractor with respect to delays and disruption to the construction works caused by variations and the late receipt of information, together with claims for additional payment.
tunnels, rail, airports, roads and bridges. more
power stations, sewerage treatment works, water treatment plants and E&M installations. more
foundations, reclamations and site formation. more
commercial and residential developments. more
Tseung Kwan O to Lam Tin Tunnel is a dual two-lane highway... more
Formation of 650 hectares of land north of the existing airport... more
The Contractor entered into two Contracts with the... more
The construction of a nine storey cultural centre block... more
The Liantang Boundary Control Point includes the... more
Staff and guests enjoy the ‘Now that’s what I call music’ themed event... more
Case Study: Bored Piling. more